top of page

Project Milestones and Industry Advances

Project Overview:

  • Capital Expenditure: $87M CAD

  • Client: Sayona Mining 

  • Increase production to 3800 tpd open pit mine operation that treats pegmatite ore by froth flotation to produce chemical-grade 6% Li2O spodumene concentrate
     

Our Mandate:

  • Owner's Team Representative

  • Engineering Management

  • Project and Construction Management

  • Procurement and Contract Management

  • Risk Management

  • Pre-operational verification and commissioning service

  • Project delivered on time and on budget

Sayona NAL Complex Process and Capacity Improvements - 2020-2024

Project Overview:

  • Capital Expenditure: $26M CAD

  • New 5500t of crushed ore storage capacity

  • Including a by-pass system and a dust collection system with particulate emission control

Our Mandate:

  • Owner's Team Representative

  • Engineering Management

  • Project and Construction Management

  • Procurement and Contract Management

  • Pre-operational verification and commissioning service

  • Project delivered on time and on budget

Sayona Crushed Ore Storage Dome - 2023-2024

Project Overview:

  • Capital Expenditure: CAD 100 Million for two spillways

  • Inauguration: 1952-1953

  • Features: 6 Valves Each, CCD at 37.8m, CCS at 39.6m

  • Hydrological Impact: Critical and Substantial


Our Mandate:

  • Project Management and Oversight

  • Conducted Cost Estimates and Risk Assessments for OoM and PFS phases

  • Managed Procurement Coordination

  • Facilitated RTA Project Approval

  • Oversaw Subcontractor Bid Analysis and Selection

Rio Tinto Project Spillways - Valve Evaluation Studies - 2023-2024

Project Overview:

  • Capital Expenditure: CAD $65 Million

  • Structure Origin: Built in 1924

  • Focus: Concrete Repairs on Downstream  Side of 11 Runners and 12 Pillars

  • Structure Height: 40.5 Meters

  • Hydrological Impact: Significant

 

Our Mandate:

  • Managed a CAD $65 Million restoration of a historic 1924 construction

  • Managed concrete repairs for critical infrastructure, including 11 runners and 12 pillars, standing 40.5 meters tall

  • Addressed significant hydrological consequences through meticulous project management

Rio Tinto CIM-Spillway 4 Study: Refurbishment Downstream Side 2023-2024

Project Overview:

  • Capital Expenditure: CAD $240 Million

  • Outcome: Increased Aluminum Billet Production to 202,000 Tons Per Year

  • Enhancements: New Furnaces, Casting Pit, Coolers, Handling, Inspection, Sawing, and Packaging Systems

Our Mandate:

  • Coordinated Engineering Efforts

  • Managed Drawing and Technical Documentation Approval Processes

  • Assisted in Machine Safety and 3D Model Design Review Meetings

Rio Tinto Centre de Billettes - Alma Exécution - 2023-2024

Project Overview:

  • Capital Expenditure: CAD $45 Million

  • Objective: Replace Railcar Fleet in the Saguenay Area

  • Inventory: 200 Alumina and 40 Calcinated Coke Railcars

  • Logistics: Enhancements at 10 Load/Unload Locations

Our Mandate:

  • Project Management and Oversight

  • Provided Cost Estimations for Order of Magnitude (OoM) and Definitive Feasibility Study (DFS)

  • Conducted Risk Assessments for OoM and DFS phases

  • Developed the Execution Plan

  • Managed Subcontractor Bid Analysis and Contract Awards

Rio Tinto - Railcars - Fleet Replacement Studies - 2023-2024

Project Overview:

  • Capital Expenditure: CAD $600 Million

  • Annual Production: 23,000 tons of Lithium Carbonate

  • Product Concentration: 6.0% Li₂O

  • Upgrades Required: Hydrometallurgical Area (including NaSO₄ crystallizer and tank addition) and Pyrometallurgical Area (enhancements to feed pre-heat, cooling system, ball mill, and furnace)
     

Our Mandate:

  • Acted as the Owner's Representative

  • Led Conversion plant scoping study and pre-feasibility study

  • Metallurgical test work management 

  • Successfully delivered the study on time and within budget

Sayona Québec Inc. - NAL Conversion Plant Technical Study - 2022-2023

Project Overview:

  • Capital Expenditure: CAD $60 Million 

  • Client: Investissement Québec

  • IPMT execution model

  • Underground mining

  • Gold processing facilities

Our Mandate:

  • Owner's technical representative

  • Advising, reviewing and ensuring the projects integrity is met for the management of the project

  • Driving habits, coordinating the tasks with team leaders

  • Ensuring industry best practices and lean principals were in place

Monarch Mining - Beaufort Mine and Beacon Mill Restart  - 2021-2022

Project Overview:

  • Capital Expenditure: EUR 1.28 Billion 

  • Client: Vulcan Energy Resources

  • Brine Extraction: Utilizing wells

  • Geothermal Plant: Converts brine heat into electricity

  • Direct Lithium Extraction (DLE) Plant Processes
     

Our Mandate:

  • Represented the Owner's Team

  • Managed and Controlled the Project Studies in PFS and DFS

  • Handled Document Control

  • Orchestrated Pilot Plants' Turnkey Package, including bid, award, and control with two firms

  • Ensured the study was delivered on time and within budget

Vulcan Energy Resources - Prefeasibility Study - 2021-2023

Project Overview:

  • Capital Expenditure: USD $1 Billion

  • Ecuador's First Large-Scale Underground Gold Mine

  • Annual Output: 310,000 Ounces over 15 Years

  • Infrastructure: 10km of Tunnels, 50km of Roads, 42km Electrical Transmission, and a Processing Plant

 

Our Mandate:

  • Served as the Owner’s Technical Advisor

  • Validated Monthly Project and Construction Progress evaluations against Budget and Schedule

  • Conducted Regular Site visits

  • Authorized Periodic Cost-to-Complete Certifications

Investor Consortium - Fruta Del Norte (Lundin Gold) - 2018-2020

Project Overview:

  • Capital Expenditure: CAD $110 Million 

  • Client: CATL

  • Lithium Reserve: 21 Mt at 0.94% Li₂O

  • Daily Processing Capacity: 3,800 tons

  • Annual Spodumene Production: 190,000 tons at 5.8% Li₂O

Our Mandate:

  • Owner's Team Representative;

  • Engineering Management

  • Project and Construction Management;

  • Project delivered on time and on budget

North American Lithium - LAN Restart - 2016-2019

Our next projects...

bottom of page